Civic participation

What you can do, and when

Most of the decisions about this project are being made by agencies, not voters, and the first deadline is close: Montana DEQ stops taking comment on the campus’s well at 11:59 p.m. on November 6, 2026.[1] This page lays out each opening, with every address and number taken from the agency’s own published sources.

Ground rules

Everything on this page is lawful, ordinary civic participation, and that is the only kind this site encourages. The contact information below is official contact information that public agencies publish so they can hear from the public. Use it civilly, on official channels, about the policy. Do not contact anyone at home, do not harass anyone, and do not go onto the site: it is private property. The officials named here are acting in their official capacities, and nothing on this site alleges unlawful conduct by any of them.

Why now

The DEQ comment period on the well

Time remaining until the DEQ public comment deadline

Calculating.

until 11:59 p.m., November 6, 2026, the deadline for public comment to Montana DEQ on the Big Sky Campus public water well.[1]

The comment period closed November 6, 2026. The next formal opening is the air quality permit for the gas plants, if and when one is filed.[12]

Counted to 11:59 p.m. Mountain Time, the deadline DEQ publishes.

Where to send it:[1]

Name the project in the subject line (“Quantica Big Sky Campus Public Water Well”). The application, the draft categorical exclusion checklist and the programmatic environmental assessment are all linked from DEQ’s comment page. Read the checklist: it is the document your comment is answering.

Points a comment can make, each grounded in the record:

  • Ask for a full environmental review. A categorical exclusion is the lightest review DEQ has. The well serves a project whose gas plants DEQ’s own staff expect to need a major air permit and likely an EIS. Ask DEQ to analyze the well as part of that whole project, not as a stand-alone well.[1][12]
  • Ask about the brine. If Madison water needs reverse-osmosis treatment, where does the reject brine go, and under what permit? See The Project.
  • Ask about the neighbors’ wells. The claim that the Madison and the Eagle aren’t connected comes from the company. Ask DEQ what independent data supports it, and what monitoring would catch it if the claim is wrong.
  • Ask about the water right. DEQ says a data center needs a DNRC water right, a change in use, or water from an existing right holder. Ask which one applies here, and whether DNRC has received an application.[2]

Short, specific and civil beats long and heated. Say where you live if you’re in Yellowstone County or rely on a well.

Local government

Yellowstone County Board of Commissioners

Regular meetings are on Tuesdays at 9:00 a.m. in Room 309 of the Ostlund Building, 2825 3rd Ave N, Billings. Each agenda has two public comment periods, one on agenda items and one on county business, at three minutes per speaker. The board cannot act on an item that wasn’t noticed on the agenda.[4] The commission also holds Thursday discussion meetings; its October 22 agenda included a presentation on the health impacts of data centers.[5]

Yellowstone County Commissioners, with the contact information the county publishes, accessed October 23, 2026.
CommissionerDistrictCounty email
Mark MorseDistrict 2 · Chair[email protected]
Chris WhiteDistrict 1[email protected]
Mike WatersDistrict 3[email protected]

The commissioners’ office: 406-256-2701, P.O. Box 35000, Billings, MT 59107.[3] Agendas are posted on the county’s commissioners page; check the agenda before going, since meeting times and rooms can change.

Worth knowing when you write: the commissioners have already asked the Legislature to amend the Right to Compute Act so it doesn’t limit county zoning or health and safety authority.[8] Asking them what they will do with that authority if they get it back is a fair question.

The utility regulator

Montana Public Service Commission

The PSC decides what NorthWestern’s other customers pay. Its front page lists the proceedings that matter here: the investigation into resource adequacy and data centers, NorthWestern’s large load tariff, the NorthWestern–Black Hills merger, and NorthWestern’s 2026 integrated resource plan.[6]

  • Online: in REDDI, choose “Continue as Guest,” then “Submit a Public Comment in a Docket.”
  • Email: [email protected]
  • Phone: 406-444-6150 or toll-free 800-646-6150
  • Mail: 1701 Prospect Ave, PO Box 202601, Helena, MT 59620-2601

The ask that runs through the November 2025 complaint is simple: a separate rate class for data centers that pays its full cost of service, so residential customers don’t.[7]

State law

The Legislature

The Right to Compute Act is state law, and only the Legislature can change it. The next session convenes in January 2027. Find your senator and representative with the Legislature’s lookup.[9] The case for changing it is on Context.

An unanswered question

Ask how loud it will be

Nothing public says how far the campus and its gas plants could be heard. The estimate on The Project is this site’s, built from general engineering ranges rather than citable sources, and is not a measurement. These are questions for the record.

  • Ask for a noise study. Request a pre-construction acoustic assessment for the whole campus and the gas generation, with predicted sound levels at the property line and at the nearest homes, day and night.
  • Ask about low-frequency sound. Cooling fans and turbines produce a hum that ordinary A-weighted decibel figures understate. Ask whether the study will measure it separately.
  • Ask how close the nearest homes are. Request a site plan showing buildings, cooling equipment and generators against the nearest residences and wells.
  • Ask what limit applies. Ask which agency, if any, can set or enforce a noise limit here, and what the company has committed to.
  • Ask about mitigation. Enclosures, silencers, berms, and where the loudest equipment would sit.

Where to ask: the county commissioners, above, at a Tuesday meeting or by email, now. The formal opening for the gas plants is DEQ’s air quality permit, if and when an application is filed; a noise question belongs in that comment period too. The well comment on November 6 is about water, so keep this one to the project as a whole.

Go prepared

Three minutes is enough, if it’s specific

The strongest comment isn’t an opinion about data centers in general. It’s a resident asking a public agency a question it hasn’t answered. This site exists so you don’t have to take anyone’s word for the facts:

Organizing on data centers statewide is under way at Northern Plains Resource Council[10] and MEIC,[11] independent organizations not affiliated with this site.

Citations

Sources for this page

  1. Montana DEQ, “Quantica Big Sky Campus Public Water Well: Request for Public Comments on Categorical Exclusion Review under a Programmatic Environmental Assessment,” posted September 29, 2026, accessed October 23, 2026. deq.mt.govMadison aquifer, about 1,000 ft deeper than the Eagle Sandstone; NE¼ SW¼ Sec. 9, T3N, R23E, about 3.5 miles southeast of Broadview; ~150,000 gpd during construction and ~20,000 gpd after; comments due 11:59 p.m., November 6, 2026 (extended). Links the application, the draft checklist and the programmatic EA.
  2. Montana DEQ, press release on the Big Sky Campus well, September 29, 2026, updated October 21, 2026. deq.mt.govDEQ’s review covers water quality; water quantity and water rights belong to the Department of Natural Resources and Conservation, from which a data center must obtain a water right, a change in use, or water from an existing right holder.
  3. Yellowstone County, Board of County Commissioners page, accessed October 23, 2026. yellowstonecountymt.govMembers, districts, emails, the shared phone 406-256-2701 and mailing address P.O. Box 35000, Billings, MT 59107.
  4. Yellowstone County, Board of County Commissioners regular meeting agenda, October 27, 2026. Agenda (PDF)Tuesday, 9:00 a.m., Room 309 of the Ostlund Building, 2825 3rd Ave N, Billings. Two public comment periods; three minutes per speaker.
  5. Yellowstone County, Board of County Commissioners discussion agendas, accessed October 23, 2026. yellowstonecountymt.govThe October 22, 2026 discussion agenda listed a presentation on the health impacts of data centers.
  6. Montana Public Service Commission, home page, accessed October 23, 2026. psc.mt.gov · REDDIPublic comment through REDDI (“Continue as Guest”, then “Submit a Public Comment in a Docket”); [email protected]; 406-444-6150 or 800-646-6150. “What’s Trending” lists an investigation into resource adequacy and data centers, NorthWestern’s large load tariff, the NorthWestern/Black Hills merger application, and NorthWestern’s 2026 integrated resource plan.
  7. Earthjustice, “Groups file complaint to stop NorthWestern Energy from shifting data center costs to residential customers,” November 18, 2025. earthjustice.orgFiled November 17, 2025 for Big Sky 55+, Butte Watchdogs, Climate Smart Missoula, Golden Triangle Resource Council, Helena Interfaith Climate Advocates, Honor the Earth, MEIC, MontPIRG and NW Energy Coalition.
  8. “Yellowstone County commissioners ask Legislature to ‘refine’ data center law,” Montana Free Press, September 24, 2026, updated October 1. montanafreepress.org
  9. Montana Legislature, legislator lookup. leg.mt.gov
  10. Northern Plains Resource Council, “Press Pause on Data Centers.” northernplains.org/data-centers
  11. Montana Environmental Information Center, data centers page. meic.org/data-centers
  12. Alex Mitchell, “Emails: Massive gas power plants planned north of Billings for Broadview data center,” Billings Gazette, May 21, 2026, as reprinted by Northern Plains Resource Council. northernplains.orgDEQ emails of March 23 and April 3, 2026: a Major NSR/PSD air permit likely needed, with public review and a likely environmental impact statement; a gas line would be needed. 585 MW of gas engines plus 1,200 MW of gas turbines.

Company statements are cited as company statements, not as findings. Corrections are welcome: corrections policy.