Independent public-record site · not affiliated with Quantica Infrastructure, NorthWestern Energy or Yellowstone County

The project, from the record

What Quantica is building outside Broadview

The company’s own releases, the state’s permit file, and the reporting on both, assembled into one account: how big the campus is, how much power it wants, what would generate that power, where the water comes from, and who is behind it. Where the company’s numbers have changed, this page shows each version and its date.

The land

The site

Quantica launched its Montana platform, Big Sky Digital Infrastructure, in August 2025, describing a campus on about 5,000 acres.[2] Its website now says 5,100 acres owned fee simple, about 30 miles north of Billings and about 3.5 miles outside Broadview.[1] The Montana Free Press describes it as nearly eight square miles.[14]

It is not a proposal on paper. Equipment staging began in early September 2026, followed by access roads and work on the well.[14]

The load

The power request

On May 20, 2026, Quantica announced it had filed interconnection applications with NorthWestern Energy for up to 7,235 megawatts.[3] The company described the campus as 1,100 MW, and told reporters it planned 500 MW in its first year and 1,100 MW by its second, and that the full request “doesn’t necessarily” mean it would use that amount.[4]

Quantica’s power figures over time, against the grid they would join.
FigureMWSource and date
NorthWestern letter of intent to serve the projectup to 1,000July 30, 2025[7]
Size at first announcement~1,000As reported, May 2026[5]
Phase 1, “beginning in 2028”500Company website, accessed Oct 23, 2026[1]
The campus, per the May 2026 release1,100May 20, 2026[3]
Interconnection applications, maximum7,235May 20, 2026[3]
NorthWestern’s average load, 2024~1,400State utility data, as reported[4]
Montana net summer generating capacity, 20247,183As reported[6]
What the record does not answer

Why a campus the company describes as 1,100 MW needs interconnection applications for 7,235 MW. And where the first building comes online: the May 2026 release says 2029, while the company’s website says Phase 1 ramps up “beginning in 2028.”[3][1]

The generation

The gas plants

In public, the company says it is “evaluating natural gas” among other sources, and that it will pay for its own generation.[1] Its chief accounting officer told reporters that NorthWestern’s ratepayers “will not be responsible for the cost of power.”[4]

The state’s own correspondence is more specific. Emails from Montana DEQ obtained by the Billings Gazette describe 585 MW of gas-fired engines and 1,200 MW of gas-fired turbines, 1,785 MW in all. After a pre-application meeting in March 2026, a DEQ air permitting staffer estimated the project would need a Major New Source Review / Prevention of Significant Deterioration permit, with public review and likely an environmental impact statement. An April email noted the plants would need a gas line.[8]

The Billings Gazette has also reported Public Service Commission filings showing NorthWestern is considering a gas storage facility near the Broadview substation.[10]

What the record does not answer

As of October 23, 2026, this site found no air quality permit application for the project on DEQ’s public listings.[9] Construction of roads and the well went ahead without one; neither requires an air permit. When an application is filed, the PSD process will be the main formal opening for public comment on the gas plants. This site has not reviewed the gas storage filing itself, only the Gazette’s headline.[10]

The sound

How far could it be heard?

No one has published an answer. This site found no noise study, no site plan showing where the buildings, cooling equipment or generators would stand, and no distance from the campus to the nearest homes. The campus is about 5,100 acres, and the generation DEQ’s emails describe is 585 MW of gas engines and 1,200 MW of gas turbines.[1][8]

This site’s estimate, not a record

These figures are general engineering ranges, not citable sources. They are rules of thumb for large data centers and gas plants, written without reference to any named study or measurement, and nothing in them is specific to this project. Treat them as an order of magnitude, not a prediction. With that caveat: the cooling fans and chillers of a campus this size are usually audible about half a mile to a mile away in quiet rural air, and at other sites residents have reported the low-frequency hum from one to two miles off, mostly at night and in cold weather. Large gas turbines and engines are the louder source. Unmitigated, they can carry one to three miles; with enclosures and silencers, closer to half a mile to a mile. Sound falls about 6 dB for each doubling of distance, so adding units makes it somewhat louder, not many times farther. Open terrain, wind direction and temperature inversions can shift all of this considerably.

What the record does not answer

How loud the campus would be at its property line, what cooling it will use, how close the nearest homes are, and whether any noise limit will apply. The questions to put to Quantica and the agencies are on Take Action.

The aquifer

The well, and the comment period on it

The campus would draw water from a new public water supply well into the Madison aquifer. The well site is in the NE¼ of the SW¼ of Section 9, Township 3 North, Range 23 East, about 3.5 miles southeast of Broadview. The Madison lies roughly 1,000 feet below the Eagle Sandstone aquifer that supplies most nearby wells.[11]

  • During construction: about 150,000 gallons a day.[11]
  • After construction: about 20,000 gallons a day, for drinking water and possibly the closed-loop cooling system.[11][13]
  • Pumping: up to 160 gallons a minute for up to 16 hours a day, by the company’s figures.[13]

The company says the Madison is not hydraulically connected to the Eagle, so neighbors’ wells would not be affected.[13] That is the company’s claim. A retired Montana Tech hydrogeologist told the Montana Free Press that Madison water in the area is warm and salty and would need reverse-osmosis treatment, which leaves a brine to dispose of.[14]

DEQ is reviewing the well under a categorical exclusion from a programmatic environmental assessment: a determination that the action does not need its own environmental assessment. DEQ’s review covers water quality. Water quantity and water rights belong to the Department of Natural Resources and Conservation, from which a data center must obtain a water right, a change in use, or water from an existing right holder.[11][12]

What the record does not answer

This site found no DNRC water right application for the project in any source it reviewed, and has not searched DNRC’s database directly. Nor does any reviewed record say where the reverse-osmosis brine would go. Accounts of the Madison’s depth also differ: DEQ says about 1,000 feet below the Eagle, while the company and the Free Press say about 1,300.[11][13][14]

Comment on the well by November 6

In everyday terms

What those numbers add up to

Megawatts and gallons a day are hard to picture. This is the same arithmetic in units a household would recognize.

This site’s arithmetic, not a record

The campus figures below are the company’s and DEQ’s, cited above. The household and swimming-pool yardsticks are general reference values, not citable sources, rounded and approximate: a typical US home uses about 10,800 kWh of electricity a year, about 1.2 kW on average; a typical household uses about 300 gallons of water a day, about 80 per person; an Olympic swimming pool holds about 660,000 gallons; Montana has roughly 450,000 households and Yellowstone County roughly 70,000. The power rows also assume the campus runs flat out all year, which this site cannot verify. A campus that ran at partial load would use proportionally less.

Power

What running continuously would equal, from the figures in the table above.
If it ran atEnergy a yearAbout the same as
500 MW (Phase 1)[1]4.4 million MWhThe electricity of about 400,000 homes, nearly as many as Montana has households, and about six times Yellowstone County’s. More than a third of NorthWestern’s whole average load.[4]
1,100 MW (the campus)[3]9.6 million MWhAbout 900,000 homes. Roughly four-fifths of NorthWestern’s average load.[4]
7,235 MW (the maximum request)[3]63 million MWhAbout 5.9 million homes. Five times NorthWestern’s average load, and slightly more than all of Montana’s net summer generating capacity.[4][6]

The 1,785 MW of gas engines and turbines DEQ’s emails describe is, on the same arithmetic, more than the 1,100 MW the company calls the campus.[8] How much of that generation would serve the campus, and how much would be sold or held in reserve, is not in the record.

Water

What the well’s stated pumping would equal.
Stated useA dayA year, if all yearAbout the same as
During construction[11]150,000 gal
~100 gal a minute
55 million gal
~170 acre-feet
The home water use of about 500 households. A swimming pool filled every four to five days.
After construction[11][13]20,000 gal
~14 gal a minute
7.3 million gal
~22 acre-feet
The home water use of about 70 households. A swimming pool filled about once a month.
What the record does not answer

How long construction pumping would last, so the yearly figure for it is an upper bound. And how much water the cooling would use: the company says 20,000 gallons a day covers drinking water and possibly closed-loop cooling,[13] but no cooling design has been published. This site’s general understanding, not a sourced claim, is that evaporative cooling uses far more water than a closed loop, so the cooling type is the number that would change this table most.

The developer

Who is behind it

  • Quantica Infrastructure, which names EnCap Investments L.P., an energy private-equity firm, as its sponsor.[3]
  • John Chesser, CEO, per the company’s 2026 releases.[3][13]
  • Charlie Baker, described as chief financial officer in 2025 and chief accounting officer in 2026.[2][4]
  • Damon Obie, Quantica’s lawyer in Yellowstone County’s initiative fight, per the Montana Free Press.[16] See Context.

No tenant has been announced. In June 2026 the company announced an agreement with the Southeastern Montana Building and Construction Trades Council; few of its terms are public.[15]

In the company’s words

What Quantica says the campus will bring

The company’s FAQ, citing the University of Montana’s Bureau of Business and Economic Research, says:[1]

  • about 2,000 Montana jobs at peak construction, about 500 of them direct;
  • about 600 ongoing jobs;
  • about $20 billion of capital spending for a 500 MW facility, about $2 billion of it in Montana.
How to read these

These are the developer’s projections, not commitments, and this site has not reviewed the underlying study. The FAQ gives no dollar figure for property taxes. They are listed here so a reader can hold the company to them.

Citations

Sources for this page

  1. Big Sky Digital Infrastructure, home page and FAQ, accessed October 23, 2026. bigskydigitalinfra.com · FAQCompany statements. 5,100 acres owned fee simple; Phase 1 ramping to 500 MW “beginning in 2028”; “evaluating natural gas”; job and investment estimates attributed to the University of Montana’s Bureau of Business and Economic Research.
  2. “Quantica Infrastructure introduces Big Sky Digital Infrastructure as its flagship development platform in Montana,” August 4, 2025, as republished by Big Sky Economic Development. bigskyeconomicdevelopment.orgThe project’s public launch; 5,000 acres at the time.
  3. Quantica Infrastructure, “Quantica files interconnection applications to expand power generation for its Big Sky Digital Infrastructure Campus,” press release, May 20, 2026. quanticainfra.comCompany statement. Up to 7,235 MW of interconnection against a 1,100 MW campus; EnCap Investments L.P. named as sponsor; CEO John Chesser; the ratepayer quote from Charlie Baker.
  4. Justin Dubail, “Big Sky data center near Billings seeks major power supply from NorthWestern Energy,” NonStop Local / Montana Right Now, May 21, 2026. montanarightnow.com7,235 MW maximum request; 500 MW in year one and 1,100 MW by year two; NorthWestern’s 2024 average load of nearly 1,400 MW, per state utility data; first building hoped for in 2029.
  5. “Quantica seeking to boost energy capacity at Broadview data center site to 7,235 MW,” KTVQ, May 2026. ktvq.comThe project had initially been announced at around 1,000 MW.
  6. “Quantica submits applications for stated 7,235 megawatts,” Montana State News Bureau, via the MSU Exponent, May 2026. msuexponent.comCompares the request to Montana’s total net summer generating capacity of 7,183 MW in 2024.
  7. “Groups file complaint to block NorthWestern Energy plan tied to data center projects,” NBC Montana, November 19, 2025. nbcmontana.comNorthWestern’s July 30, 2025 letter of intent to provide up to 1,000 MW to Quantica’s project.
  8. Alex Mitchell, “Emails: Massive gas power plants planned north of Billings for Broadview data center,” Billings Gazette, May 21, 2026, as reprinted by Northern Plains Resource Council. northernplains.orgDEQ emails of March 23 and April 3, 2026: a Major NSR/PSD air permit likely needed, with public review and a likely environmental impact statement; a gas line would be needed. 585 MW of gas engines plus 1,200 MW of gas turbines.
  9. Montana DEQ, air quality permit listings, accessed October 23, 2026. deq.mt.gov/airNo entry for Quantica, Big Sky Campus or Broadview was found on October 23, 2026.
  10. “PSC filings reveal NorthWestern plan for gas storage facility near Broadview substation,” Billings Gazette. billingsgazette.comPaywalled. This site has relied only on the headline and has not reviewed the underlying filing.
  11. Montana DEQ, “Quantica Big Sky Campus Public Water Well: Request for Public Comments on Categorical Exclusion Review under a Programmatic Environmental Assessment,” posted September 29, 2026, accessed October 23, 2026. deq.mt.govMadison aquifer, about 1,000 ft deeper than the Eagle Sandstone; NE¼ SW¼ Sec. 9, T3N, R23E, about 3.5 miles southeast of Broadview; ~150,000 gpd during construction and ~20,000 gpd after; comments due 11:59 p.m., November 6, 2026 (extended). Links the application, the draft checklist and the programmatic EA.
  12. Montana DEQ, press release on the Big Sky Campus well, September 29, 2026, updated October 21, 2026. deq.mt.govDEQ’s review covers water quality; water quantity and water rights belong to the Department of Natural Resources and Conservation, from which a data center must obtain a water right, a change in use, or water from an existing right holder.
  13. Big Sky Digital Infrastructure, “Big Sky Digital Infrastructure outlines water use plans, estimates 20,000 gallons of water per day once completed,” press release, August 31, 2026. quanticainfra.comCompany statement. Closed-loop cooling; ~20,000 gpd in operation, up to 150,000 gpd at peak construction; 160 gpm for up to 16 hours a day; the company’s claim that the Madison is not hydraulically connected to the Eagle.
  14. Phoebe Tollefson, “Broadview area data center sees first phase of construction with roads, well work,” Montana Free Press, September 18, 2026. montanafreepress.orgStaging in early September, then access roads and the well; a site of nearly eight square miles; a retired Montana Tech hydrogeologist on the Madison’s warm, salty water and the reverse-osmosis brine it would leave.
  15. “Agreement between data center developer and union federation thin on details,” Montana Free Press, June 17, 2026. montanafreepress.org
  16. Phoebe Tollefson, “Yellowstone County sues over initiative aimed at Quantica data center,” Montana Free Press, October 7, 2026. montanafreepress.org

Company statements are cited as company statements, not as findings. Corrections are welcome: corrections policy.