How the Broadview data center got here
One project, dated and sourced, from the state law that framed it to the deadlines still ahead. Background on the law, the county and the utility is on Context.
Entries tagged [State record] or [County] come from agency pages and agendas; [Company] entries from Quantica’s own releases, reported as the company’s statements; [Press], [Court] and [PSC] entries from named news reports and filings. Every entry is footnoted.
-
2025 session
Montana passes the Right to Compute Act State law
SB 212, sponsored by Sen. Daniel Zolnikov, R-Billings, passes the House 61–38 and the Senate 50–0. It limits government restrictions on computing to those “demonstrably necessary and narrowly tailored.”[1][2]
-
July 30, 2025
NorthWestern signs a letter of intent to serve the project Utility
Up to 1,000 MW for Quantica’s campus between Broadview and Billings.[3]
-
August 4, 2025
Quantica launches Big Sky Digital Infrastructure Company
The company introduces its “flagship” Montana platform on about 5,000 acres.[4]
-
October 20, 2025
NorthWestern and Black Hills Corp. file to merge Utility
A merger application goes to the PSC; news reports give the docket as 2025.10.078.[5]
-
November 17, 2025
Nine groups file a PSC complaint over data center costs PSC
Represented by Earthjustice, they ask for a separate data center rate class.[6]
-
February 24, 2026
NorthWestern moves to dismiss the complaint PSC
Its letters of intent with three data center developers then total about 1,400 MW.[7]
-
March 23 – April 3, 2026
DEQ emails: a major air permit, and likely an EIS State record
After a pre-application meeting, DEQ staff estimate the gas plants would need a Major NSR/PSD permit with public review and likely an environmental impact statement; a gas line would be needed.[8]
-
May 20–21, 2026
Quantica applies for up to 7,235 MW Company
Interconnection applications with NorthWestern, for a campus the company describes as 1,100 MW. The next day the Billings Gazette reports 1,785 MW of planned gas engines and turbines.[9][10][8]
-
June 17, 2026
A labor agreement, thin on details Company
Quantica announces an agreement with the Southeastern Montana Building and Construction Trades Council.[11]
-
June 18, 2026
A public panel in Broadview Community
MEIC hosts a panel on the proposal in Broadview.[12]
-
July 13 – August 2026
The first initiative is stopped Court
The petition misses a July 13 deadline; a District Court upholds its invalidation. 16,650 valid signatures were required.[13]
-
August 2026
Residents ask for emergency interim zoning County
The commission agrees to discuss it and takes no action.[14]
-
August 31, 2026
The company publishes its water plan Company
About 20,000 gallons a day once built, up to 150,000 during construction, from the Madison aquifer.[15]
-
Early September 2026
Construction begins Press
Equipment staging, then access roads and work on the well.[16]
-
September 22, 2026
Commissioners ask the Legislature to amend the law County
A letter asks the county’s delegation to change the Right to Compute Act in 2027 so it doesn’t limit county zoning or health and safety authority.[17]
-
September 29, 2026
DEQ opens public comment on the well State record
Reviewed as a categorical exclusion under a programmatic environmental assessment.[18][19]
-
October 6, 2026
The county sues to keep the second initiative off the ballot Court
A 3–0 vote to file a validity lawsuit against the initiative aimed at the May 2027 election.[20]
- October 21, 2026 DEQ extends the comment period State record
-
October 22, 2026
Health impacts of data centers on the commission’s agenda County
A presentation at the commission’s Thursday discussion meeting.[21]
-
October 25–27, 2026
The county attorney resigns County
Scott Twito’s resignation takes effect October 25; the commission takes up an interim appointment October 27.[22]
-
November 6, 2026
DEQ comment deadline on the well Deadline
11:59 p.m. How to comment.[18]
-
May 4, 2027
The election the second initiative is aimed at Ballot
If the courts allow it to proceed.[17]
-
2028–2029
First power, by the company’s schedules Company
The website says Phase 1 ramps up “beginning in 2028”; the May 2026 release says the first building is expected to be operating in 2029.[23][9]
Sources for this page
- “Right to Compute Act and regulatory authority,” Montana Free Press, September 21, 2026. montanafreepress.org
- Montana Code Annotated § 2-10-204 (Right to Compute Act; Ch. 150, L. 2025, codified at MCA 2-10-201 through 2-10-207). mca.legmt.gov
- “Groups file complaint to block NorthWestern Energy plan tied to data center projects,” NBC Montana, November 19, 2025. nbcmontana.com
- “Quantica Infrastructure introduces Big Sky Digital Infrastructure as its flagship development platform in Montana,” August 4, 2025, as republished by Big Sky Economic Development. bigskyeconomicdevelopment.org
- NorthWestern Energy, “NorthWestern Energy and Black Hills Corp. advance plans to merge,” October 20, 2025. northwesternenergy.com
- Earthjustice, “Groups file complaint to stop NorthWestern Energy from shifting data center costs to residential customers,” November 18, 2025. earthjustice.org
- “NorthWestern tells PSC to throw out data center complaint,” Daily Montanan, March 17, 2026. dailymontanan.com
- Alex Mitchell, “Emails: Massive gas power plants planned north of Billings for Broadview data center,” Billings Gazette, May 21, 2026, as reprinted by Northern Plains Resource Council. northernplains.org
- Quantica Infrastructure, “Quantica files interconnection applications to expand power generation for its Big Sky Digital Infrastructure Campus,” press release, May 20, 2026. quanticainfra.com
- Justin Dubail, “Big Sky data center near Billings seeks major power supply from NorthWestern Energy,” NonStop Local / Montana Right Now, May 21, 2026. montanarightnow.com
- “Agreement between data center developer and union federation thin on details,” Montana Free Press, June 17, 2026. montanafreepress.org
- Montana Environmental Information Center, “Recording of panel: Broadview, Montana’s largest data center proposal,” posted July 16, 2026. meic.org
- “Yellowstone County data center ballot initiative stopped by courts,” Daily Montanan, August 15, 2026. dailymontanan.com
- “Commissioners agree to discuss emergency zoning request over proposed Broadview data center,” KTVQ, August 2026. ktvq.com
- Big Sky Digital Infrastructure, “Big Sky Digital Infrastructure outlines water use plans, estimates 20,000 gallons of water per day once completed,” press release, August 31, 2026. quanticainfra.com
- Phoebe Tollefson, “Broadview area data center sees first phase of construction with roads, well work,” Montana Free Press, September 18, 2026. montanafreepress.org
- “Yellowstone County commissioners ask Legislature to ‘refine’ data center law,” Montana Free Press, September 24, 2026, updated October 1. montanafreepress.org
- Montana DEQ, “Quantica Big Sky Campus Public Water Well: Request for Public Comments on Categorical Exclusion Review under a Programmatic Environmental Assessment,” posted September 29, 2026, accessed October 23, 2026. deq.mt.gov
- Montana DEQ, press release on the Big Sky Campus well, September 29, 2026, updated October 21, 2026. deq.mt.gov
- Phoebe Tollefson, “Yellowstone County sues over initiative aimed at Quantica data center,” Montana Free Press, October 7, 2026. montanafreepress.org
- Yellowstone County, Board of County Commissioners discussion agendas, accessed October 23, 2026. yellowstonecountymt.gov
- Yellowstone County, proposed resolution appointing an interim county attorney, on the October 27, 2026 agenda. Resolution (PDF)
- Big Sky Digital Infrastructure, home page and FAQ, accessed October 23, 2026. bigskydigitalinfra.com · FAQ
Company statements are cited as company statements, not as findings. Corrections are welcome: corrections policy.